U.S. General Services Administration
Historic Preservation Technical Procedures


04211-02
REMOVING AND REPLACING DETERIORATED BRICK MASONRY


PART 1---GENERAL

1.01 SUMMARY

     A.   This procedure includes guidance on removing and
          replacing deteriorated brick masonry.  It should be used
          in conjunction with the procedure on repointing historic
          masonry.  For guidance on repointing, see 04520-02-R
          "Repointing Masonry Using Lime Mortar".

     B.   See 01100-07-S for general project guidelines to be
          reviewed along with this procedure.  These guidelines
          cover the following sections:

          1.   Safety Precautions

          2.   Historic Structures Precautions

          3.   Submittals

          4.   Quality Assurance

          5.   Delivery, Storage and Handling

          6.   Project/Site Conditions

          7.   Sequencing and Scheduling

          8.   General Protection (Surface and Surrounding)

          These guidelines should be reviewed prior to performing
          this procedure and should be followed, when applicable,
          along with recommendations from the Regional Historic
          Preservation Officer (RHPO).

     C.   For general information on the characteristics, uses and
            problems associated with brick, see 04211-08-S.

1.02 PROJECT/SITE CONDITIONS

     A.   Environmental Requirements:

          1.   Do not proceed with brick replacement under adverse
               weather conditions, or when temperatures are below
               or above manufacturer's recommended limitations for
               installation;  Proceed with the work only when
               forecasted weather conditions are favorable for
               proper cure.

          2.   Wet Weather:  Do not apply or mix mortar on outside
               surfaces with standing water or outside during
               rain.

          3.   Cold Weather, winter construction is not allowed
               without consent of RHPO;  Winter construction when
               surface temperature of masonry is below 40o F. or
               air temperature is predicted to be below 40o F.
               within 48 hours.  See #6 below.

          4.   Hot Weather:  The surface temperature of the work,
               not the ambient temperature, should not be higher
               than 100o F.; Mortar mixing should be done only in
               the shade; Cover mortar with water-misted burlap in
               hot weather to reduce evaporation; Pointing work
               should be done in the shade;  Work around the
               building during the day so that the fresh work will
               be shielded from direct sunlight to reduce
               evaporation rate.  High temperatures can cause
               flash setting of cements and rapid evaporation of
               water in the mix, leading to lack of development of
               final strength by the cement. 

          5.   All materials must be kept above 40o F.

          6.   Special Precautions and Notes:  Do not allow
               masonry to freeze until mortar is thoroughly dry
               and hardening almost complete (approx. three days
               time); The setting of lime mortar is very much
               slower than that of cement mortar because the
               curing requires the absorption of carbon dioxide to
               form hard lime carbonates; It is a very lengthy
               process, so do not expect it to become hard
               immediately, especially at the core of large masses
               of masonry.


PART 2---PRODUCTS


2.01 MATERIALS

     A.   Salvaged Brick:  Approved by RHPO, sound, crack free,
          clean brick without face chips larger than 1/2 inch,
          salvaged from removal of removed face brick work of same
          type.

     B.   Replacement Brick:  Approved by RHPO.

     C.   Brick slips:  Approved by RHPO.

     D.   Mortar to match existing (see 04100-03-S "Preparing Lime
          Mortar for Repointing Masonry").

2.02 EQUIPMENT

     A.   Trowel

     B.   Joint tools

     C.   Chisel

     D.   Hawk

     E.   Hammer

     F.   Stiff bristle brushes


PART 3---EXECUTION

3.01 EXAMINATION

     A.   Deterioration of brick due to moisture is evident as
          spalling, erosion, cracking, peeling paint, and
          deteriorated mortar joints. 

     B.   Some causes of brick deterioration include:  a) Rising
          damp, b) the accumulation of dissolved acids carried by
          rainwater and condensation, c) soluble salts
          crystallizing in the pores of the brick face, d)
          alternate freezing and thawing, and e) the accumulation
          of dirt and air-borne particles on the exterior surface.

3.02 PREPARATION

     A.   Surface Preparation:

          1.   Wet brick having absorption rates greater than
               0.025 oz. per sq. inch per minute.

               a.   On the flat side of a brick, deposit water on
                    an area approximately the size of a 25 cent
                    coin.

               b.   If the water disappears in less than 30
                    seconds, wet the bricks.

          2.   Absorptive brick should be thoroughly soaked in the
               pile each afternoon prior to the day they are to be
               used.

          3.   Cover the bricks with tarps or heavy paper to
               prevent evaporation. 

          4.   Wet brick as necessary during the day; Sprinkle the
               brick pile with a hose for a period long enough for
               water to run down the side of the pile; Use wetting
               methods which ensure that each masonry unit is
               nearly saturated but surface dry when laid; (DO NOT
               wet stone masonry units).

          5.   Repair flashing if necessary.

          6.   Where fresh masonry joins existing work, clean the
               exposed surface of the set masonry by removing
               loose brick and mortar and wet lightly to obtain
               the best possible bond with the new work.

3.03 ERECTION, INSTALLATION, APPLICATION

     A.   Replacing Deteriorated Masonry with Brick slips:  The use
          of brick slips should be limited to replacement of
          individual bricks or to small areas of brickwork.

          NOTE:  Brick slips are brick facings about 1 inch thick. 
          They are used when damage to adjacent sound brickwork is
          likely to occur if full-size replacement is attempted.

          1.   Cut out the deteriorated masonry to a regular
               shape.

          2.   Clean the cavity of loose mortar and other debris
               by hand using a chisel and stiff bristle brushes.

          3.   Solidly set the slip in a bed of mortar.

     B.   Replacing Deteriorated Units with Full-Size Bricks:

          1.   Carefully remove deteriorated brick units by hand
               using a hammer and chisel.

          2.   Rebuild back-up and substrate as required to
               replace any unsound material that was removed.  

          3.   Clean the cavity of loose mortar and other debris
               by hand using a chisel and stiff bristle brushes.

          4.   Lightly wet the exposed brick surfaces.


          5.   Lay brick units with completely filled bed and head
               joints; Butter ends with sufficient mortar to fill
               head joints and shove into place.  

               NOTE:  Lay masonry plumb and true following the
               coursing and patterns of the adjacent existing
               sound construction; Level off work at required
               heights and form beds to build-in salvaged or moved
               materials.

          6.   If adjustments are required, remove units, clean
               off mortar and reset in fresh mortar.  

          7.   Blend new work into existing work smoothly with no
               lines of demarcation and no change of pattern or
               coursing.

          8.   Rake all joints in replacement work to receive tuck
               pointing; Joints up to 3/8" in width shall be raked
               to a depth of 1/2"; Joints 3/8" in width shall be
               raked to a depth of 1". 

          9.   Brush all excess mortar from the wall surface
               frequently during the work; Protect all existing
               surfaces from mortar dripping and splashing.

3.04 ADJUSTING/CLEANING

     A.   Clean off adjacent surfaces which have been spattered
          during the course of the work.  Rinse immediately with
          clean, clear water.

     B.   Wipe all excess mortar as the work progresses.  Dry brush
          at the end of each day's work.  

     C.   After mortar is thoroughly set and cured, remove loose
          mortar and dirt from new masonry surfaces.

     D.   Wash down the masonry surface with clean, clear water.

                          END OF SECTION

Back to Historic Preservation Technical Procedures Index